IRRIGATION PROFILE
SRIKAKULAM DISTRICT
This district lies in the following river basins as below
| S.No. |
Name of the Basin |
% of area covered |
| 1. |
Vamsadhara River Basin |
33.11% |
| 2. |
Nagavali River Basin. |
31.33% |
| 3. |
Bahuda River Basin |
4.91% |
| 4. |
Mahendra tanaya river basin. |
7.54% |
| 5. |
Pundi Drainage Basin |
6.25% |
| 6. |
Nowpada Minor Drainage Basin |
14.05% |
|
The major amount ofrainfall is during the South-West monsoon and/or North-East monsoon and the normal rainfall is 1162 mm. The statistical data of the district is as follows.
|
| 1. |
Geographical Area |
5,84,300 |
Ha. |
| 2. |
Population (2001) |
2528491 |
|
| 3. |
Culturable Area |
3,12,016 |
Ha. |
| 4. |
Forest Area |
70,841 |
Ha. |
| 5. |
Barren & Un Cultivable Area (2003) |
50,427 |
Ha. |
| 6. |
Land put to Non-Agricultural purpose (2003) |
89,427 |
Ha. |
| 7. |
Sown Area (2003) |
3,12,016 |
Ha. |
| 8. |
Irrigated Area (2001) |
1,67,036 |
Ha. |
| 9. |
Normal Rainfall (2003) |
1162 |
mm |
Following are the details of Irrigation Projects benefiting the district
I. COMPLETED PROJECTS
A. Major Projects:Nil
B.Medium Irrigation Projects:
| Sl.No |
Name of the Project |
Ayacut Created |
Ayacut Utilised |
|
|
in Acres |
in Acres |
| 1. |
Narayanapuram Anicut |
33,701 |
33,701 |
| 2. |
Thotapalli Regulator |
30,485 |
30,485 |
| 3. |
Pydigam Project |
5,187 |
5,187 |
|
Total |
69,373 |
69,373 |
C.Minor Irritgation Projects:
1030 Schemes are existing benefiting an ayacut of 1,66,034 acres.
II. ONGOING PROJECTS:
A. Major Projects
1. Vamsadhara Project Stage I (LMC):
The project is under construction, across the river vamsadhara near Gotta village, Hiramandalam Mandal to create a total IP of 1,48,230 Acres in the district of Srikakulam. The estimated cost of the Project is Rs.8.78 Crores and an amount of Rs.107.61 Crores is spent and created an ayacut of 1,47,936 Acres (03/2003).
2.Vamsadhara Project Stage II Phase I of Stage II (RMC):
The project is under construction, across the river Vamsadhara near Gotta village, Hiramandalam Mandal to create a total IP of 62,280 acres in the district of Srikakulam. The estimated cost of the project is Rs. 123.936 Crores and an amount of Rs. 37.125 Crores is spent and created an ayacut of 19,858 acres (03/2003).
B. Medium Irrigation Projects:
1.Madduvalasa:
The project is under construction, across the river Suvarnamukhi near Madduvalasa village, Vangar Mandal to create a total IP of 24,700 acres in the district of Srikakulam. The estimated cost of the project is Rs. 8.47 Crores and an amount of Rs. 120.80 Crores is spent and created an ayacut of 11,900 acres (03/2003).
C. Minor Irrigatiion Projects:
2 Schemes are under execution to benefit an ayacut of 3387 acres in the following mandals.
|
| Sl.No |
Mandal |
Name.of Scheme |
Aayacut completed |
Estimated cost |
Programme For completion. |
| 1. |
Palakonda |
Peddagedda Reservoir |
2100 Acres. |
875.25 Lakhs |
6/2005 |
| 2. |
Melliaputti |
Varahalugedda |
1237 |
76.54 Lakhs |
6/2005 |
III. CONTEMPLATED PROJECTS:
A. Major Projects:
1. Vamsadhara Project – Phase II of Stage II:
The project is proposed to construct across the river Vamsadhara near Neradi village, Srikakulam District at an estimated cost of Rs.739 Crores (99-2000) to create a total IP of 45000 acres in the district of Srikakulam. The detailed Investigation of the Project is in progress and programmed to be completed after obtaining the concurrence of Orissa and clearance from C.W.C. –
2. Thotapally Barrage Project:
The project is proposed to construct across the river Nagavali at Thotapally Village, Vizianagaram District at an estimated cost of Rs. 415.87 Crores to create an IP of 1,84,000 Acres in the districts of Vizianagaram (71,111 Acres), Srikakulam (1,12,889 Acres). The detailed investigation of the Project is completed. The required clearances are expected to be completed by 2/2004 year.
|
B.Medium Irrigation Projects:Nil
C. Minor Irrigation Projects:Nil
IV
I.APERP
1. Vamsadhara Project.
| 1. |
Budget for 2003-04 |
= |
Rs.100.00 Lakhs. |
| 2. |
Expenditure to end of 31.1.04 |
= |
Rs. 74.55 Lakhs. |
| 3. |
Ayacut Benefitted |
= |
1,68,000 Acres |
2. Medium & Minor
| 1. |
Narayanapuram Anicut Scheme |
Rs.56.93 L |
Rs.56.71 L |
| 2. |
Nagavali River System. |
Rs.69.54 L |
Rs.47.76 L. |
| 3. |
Pydigam Project. |
Rs. 8.95 L. |
Rs. 8.92 L. |
2.APHM & ECRP: NIL
3.APERP-MI-MR: NIL
4.APSIDC: NIL
5.BREACH CLOSING WORKS.
445 No.of works breached. Amount reported for
1. Temporary restoration = Rs.145.02 L.
2. Permanent restoration = Rs.553.05 L.
TSP
|
22 No of schemes, costing Rs.59.71 Lakhs are proposed to be taken up under TSP to benefit an ayacut of 240 acres.
|
V. DETAILS OF BUDGET & EXPENDITURE 2002-03.
| Sl.No |
PROJECT |
SOURCES OF FUNDING |
BE |
EXPENDITURE |
| 1. |
Vamsadhara Project |
|
|
|
|
|
RIDF.IV. |
914.50 |
651.03L |
|
|
RIDF.II |
16.37 L |
1.19 L |
|
|
AIBP. |
981.86 L |
94.77 L. |
|
|
EAP.(APERP) |
130.32 L |
77.18 L. |
|
|
Total |
1143.05L |
824.17L. |
| 2. |
Madduvalasa Reservoir Project |
AIBP. |
1347.81 L |
1284.00 L. |
| 3. |
Medium & Minor Irrigation. |
|
|
|
|
Narayanapuram Anicut |
LOC |
26.98L. |
26.98L. |
|
Nagavali river system. |
LOC |
73.93 L . |
73.93 L. |
|
Pydigam project. |
LOC |
4.13 L |
4.13 L. |
VI. TOTAL INVESTMENT MADE ON THE IRRIGATION PROJECTS/SCHEMES SINCE INCEPTION/INDEPENDENCE is Rs.328.30 CRORES.
|